Construction works September 2020 – January 2021

Port of Melbourne is undertaking three construction projects commencing September 2020. Each project will involve some pile driving activity. Residents and port tenants may experience noise from the piling driving and related activity.  We will work closely with our contractors to minimise these impacts.

Project 1 – Short Road Wharf – commencing September 2020

Project 2 – Mooring Dolphin Works, Webb Dock – early works commencing January 2021, main work commencing February 2021

Project 3 – Gellibrand Pier Works – March 2021

Project 1 – Short Road Wharf

*update – piling works are now complete.

Port of Melbourne is constructing a new marine maintenance facility at Short Road Wharf, along the Yarra River. Some pile driving will be required. Pile driving took take place from 10 September to 24 September and was slightly extended due to weather conditions.  The new facility will enable the relocation of the former maintenance facility at Ann St, Williamstown to Short Rd Wharf. The works include:

  • construction of a structural steel metal clad store/workshop (approx. 500m2);
  • office building for up to 10 staff and amenity facilities for up to 20 staff;
  • car parking and open space amenity;
  • asphalt paving of Short Road Track; and
  • construction of concrete hardstand area and bitumen pavements.

A key project objective is to incorporate sustainability best practice in design and construction to assist the achievement of Green Star Certification, supporting Port of Melbourne’s sustainability goals.

The construction program is currently as follows:

  • Contractor mobilised to site on 10 September 2020
  • Construction period is 26 weeks
  • Pile driving (16 piles) was completed on 24 September

Project 2 – Mooring Dolphin works, Webb Dock

Works to construct a mooring dolphin will be undertaken between January and March 2021. Mooring dolphins are structures that help secure vessels when berthed. The following piling activity will take place:

A temporary support structure will be set up, including some minor temporary piling works, scheduled from 18 to 21st December.

There will be limited night time works as tidal conditions have prevented the installation of a temporary platform being done during the day. Works include pile cutoffs and beam installation.  The main works will involve an oxy torch and welding on the beams and there will be limited crane activity as the crane will be used to support the installation.  We do not anticipate any noise to affect our tenants or neighbours, but, if you have any concerns, please contact us on 1300 857 662, email community@portofmelbourne.com or register a non-emergency incident here.

The main piling work will take place February to March 2021.  Works will be scheduled between 7.00am-5.00pm during the week, and possibly on Saturdays (7am-1pm). We will regularly update this page, and provide updates on our Facebook page and via Twitter (follow us @portofmelbourne).

Project 3 – Gellibrand Pier works

Pier works are tentatively scheduled at Gellibrand Pier in early 2021. The scope of works includes:

  • Demolition of three mooring dolphins including extraction or cutting off of the existing piles.
  • Driving of a total of six steel piles
  • Installation of two precast concrete dolphin caps and associated furniture including quick release hooks.
  • Concrete remediation to limited areas on the pier head, fire monitor tower and outer mooring dolphin soffits.

More information on timing and duration of the piling works will be provided once a contractor has been engaged for the works.

There will be some noise or vibration during the day as we undertake these works. We will work closely with our contractors to minimise these impacts. If you have further questions, please contact us at community@portofmelbourne.com or 1300 857 662.